How do you plan process routing for small batches with many variants?
Three steps: group by feature family and setup, generate an operation chain per group, then merge batches by due date.The process skeleton is deterministic; the model only fills in local parameters and operation content, it does not decide the operation order.
Why the model should not order the operations
Operation order decides setup count, cost and machine conflicts, which are deterministic rules. Let the model decide the order means handing the plant's process rules to a probabilistic output.
It splits into two layers: the skeleton comes from the plant's process rules (which features are machined first, on which machine, which orders are forbidden); the parameters and content come from the model (specific cutters, cutting parameters, operation notes, review comments). A skeleton change needs a release; a parameter change does not touch the flow.
Five steps to a process route
- Collect the drawings: store STEP models and 2D drawings with their revision numbers. The drawing store is append-only, and mixing a new 3D revision with an old 2D revision is rejected by the gate.
- Group the features: group by feature family and setup requirement, so features that share a setup land on the same operation chain.
- Generate the operation chain: for each group, generate the operation chain from the plant's own process skeleton and bind cutters and cutting parameters.
- Compute takt and cost: compute takt time and cost from the plant's equipment specifications and rates, never from defaults.
- Review and write back: after a process engineer confirms, the process card goes back to MES with a bound config_version, and the run can be replayed per work order.
A concrete example
20 parts, 5 variants, due dates split across three batches. Grouping yields 3 setup routes, and merging by due date gives 3 batches — changeover drops from 5 to 3.
| Batch | Parts | Setup route | Changeover |
|---|---|---|---|
| B1 | Flange faces on 5 part types | Face → boring | 1 |
| B2 | Hole sets on 3 part types | Drill → tap → inspect | 1 |
| B3 | Remaining parts | Mill slot → deburr | 1 |
Each part inside a batch still keeps its own process card, and the bound config_version can be replayed order by order.
Frequently asked
Q: Can the model decide the operation order?
Not recommended. Operation order decides setup count, cost and machine conflicts, which are deterministic rules and should come from the plant's own process skeleton; the model only fills in local parameters, operation content and notes.
Q: How do you merge batches across variants?
By due date and material batch. Parts with the same due date and the same setup conditions go into one batch, and changeover cost is counted by setup count, not by variant count.
Q: Can you do it without historical work orders?
Yes. The process skeleton comes from the plant's own process rules and does not need historical work orders; historical orders only add parameters such as cutter preferences and actual cycle times.
Q: Is it worth it for a small shop?
Start with one line or one workstation, run a shadow run to validate, then expand by workstation. Drawing parsing and visual inspection can each be deployed as a single workstation.